NERC compliance automation software · for compliance program owners and engineering firms

We surface the evidence. You own the audit.

Your NERC evidence is already there, buried in settings files, drawings, maintenance records and event files. data phleet pulls it out, organizes it requirement by requirement, and shows you what's missing or overdue. Find the gaps before your auditor does.

11 standards + asset inventoryReports and pre-filled RSAWsCloud, hybrid or on-premise

PRC-030-1 · R1 event screeningillustrative · simulated plant
Real power output during the event Output holds at 74.9 MW, then falls to 0 MW within 0.2 seconds of the trigger. The 4-second evaluation window and the 20 MW reduction threshold from PRC-030-1 R1 are marked. Met-station irradiance stays flat through the window. pre-event − 20 MW R1 window: 4 s GHI, met station (scaled): steady -2s+0s+2s+4s+6s050100 MW
Record
SOLAR_SITE_01_UV_20261110_204826.cfg
Recorder
DFR-01 · COMTRADE 1999
Trigger (UTC)
2026-11-10 20:48:26.552
Nameplate
100.0 MW
Output
74.9 MW → 0.0 MW
  • Change ≥ 20 MW74.9 MW ✓
  • Change ≥ 10% of nameplate74.9% ✓
  • Within 4 s0.2 s ✓
  • Excluded: irradiance changeno, GHI flat
  • Excluded: dispatch / outage / testno
  • Analog causeUV (27) trip
NEEDS MITIGATIONQualifying event under R1. No exclusion applies. R2 analysis due by Feb 8, 2027 (90 calendar days).
Inspect the evidence behind this finding

Input: simulated COMTRADE record, 100 MW nameplate and steady irradiance.

Method: compare the change in real power with R1 thresholds; review each exclusion before identifying an event for R2 analysis.

Human review: your team confirms channel mapping, plant rating, event context and exclusions. Flagging the event starts the clock; the R2 root-cause analysis is still engineering work.

Read the requirement and evidence checklist →
logic: prc-030-1/r1 · deterministicreview: pending

Assemble. From the files you already have.

Surface the gaps. Missing, overdue, inconsistent.

Report. Workbook, report and RSAW.

02 / See it happen

Press a button. Watch the evidence surface.

At RE+ 2026 our booth ran a simulated 100 MW solar plant behind real SEL hardware: an SEL-710 relay whose front-panel buttons start a grid disturbance, and an SEL RTAC polling the plant. Each press trips the plant, the disturbance recorder writes a COMTRADE file, and data phleet screens it against PRC-030-1 R1 on its own. This is that demo, replayed in your browser.

SOLAR SITE 01 one-lineplant tripped
Demo plant one-line diagram A 230 kV utility grid feeds a POI breaker, a step-up transformer, a 34.5 kV collector and four inverters with their PV arrays. The selected scenario's grid event is drawn left of the grid bus, and a gauge shows the POI frequency or voltage against its trip settings. Remote generator trips OFFLINE Large load drops off Fault on the 230 kV line Capacitor bank switched in 230 kV grid 52-POI OPEN GSU 34.5 kV inverters + PV POI voltage 0.6 1.4
Plant output
0.0 MW
Frequency
60.00 Hz
Voltage
0.75 pu
Irradiance
820 W/m²
  1. Disturbance
  2. Protection
  3. COMTRADE
  4. data phleet
PRC-030-1 · R1 event screeningreplay
Record
SOLAR_SITE_01_UV_20261110_204826.cfg
Output
74.9 MW → 0.0 MW
  • Change ≥ 20 MW74.9 MW ✓
  • Change ≥ 10% of nameplate74.9% ✓
  • Within 4 s0.2 s ✓
  • Excluded: irradiance changeno, GHI flat
  • Analog causeUV (27) trip
NEEDS MITIGATIONQualifying event under R1. No exclusion applies. R2 analysis due in 90 calendar days.
logic: prc-030-1/r1 · deterministicreplay, sped up

03 / Coverage

Eleven NERC standards, organized for your audit today.

Standard-by-standard detail
Explore all 11 standards and asset inventory Inputs, gaps flagged and deliverables
StandardSubjectWhat data phleet gathers and flags
PRC-005-6Protection System MaintenanceMatches every component to its PSMP interval and latest maintenance record; flags overdue and undocumented maintenance; pre-fills the RSAW.
PRC-019-2Voltage Regulating Controls CoordinationGathers limiter, protection and capability records per unit, tracks the five-year and 90-day clocks, and flags what the coordination study is missing.
PRC-024-4Frequency and Voltage Protection SettingsReads 27/59/81 settings from the relay files, plots them against the no-trip zones, and flags elements for engineering review.
PRC-025-2Generator Relay LoadabilityKeeps load-responsive relay settings and capability data together per unit, and flags missing data and settings changes.
PRC-028-1IBR Disturbance MonitoringShows which required elements have SER, fault recording and DDR coverage on file, and flags gaps in configuration and time sync.
PRC-029-1IBR Ride-throughOrganizes ride-through settings and documentation per inverter, and assembles and tracks the R4 hardware-exemption record.
PRC-030-1Unexpected IBR Event MitigationScreens every disturbance record against the R1 thresholds and exclusions, flags qualifying events and starts the R2 clock.
FAC-008-5Facility RatingsTies each Facility Rating to its series equipment records, and flags missing or inconsistent ratings data instead of assuming it.
CIP-002-5.1aBES Cyber System CategorizationOrganizes your asset list against the impact-rating criteria and keeps the 15-month review and CIP Senior Manager approval current.
CIP-003-9Security Management ControlsReviews policies, the low impact plan sections (now including vendor remote access) and CIP Senior Manager records for gaps.
CIP-004-7Personnel and TrainingBuilds the personnel matrix and flags lapsed training, PRAs, access reviews and late revocations, requirement by requirement.
InventoryAsset InventoryReads one-lines, network diagrams and nameplates into a structured inventory of generation, transmission and cyber assets.

PRC-024-4 took effect October 1, 2026 for synchronous generators, Type 1 and 2 wind and synchronous condensers; inverter-based resources moved to PRC-029-1. MOD-025-2, MOD-026-2 and VAR-002-4.1 are next. See every date.

04 / From scattered records to audit-ready evidence

  1. Upload what you already have

    Relay settings files, one- and three-line diagrams, nameplates, maintenance records, COMTRADE event files, HR and access exports. No reformatting, no templates to fill in.

  2. Organize

    Document models pull the values out (settings, ratings, test dates, channels, names) and file each one against its asset and requirement, with a pointer to the source page. Anything it can't read with confidence is flagged, never assumed.

  3. Surface the gaps

    Fixed rules per requirement, written with former Regional Entity compliance staff, show what's missing, overdue or inconsistent. Same records, same result, every time.

  4. Resolve and report

    Your team closes the gaps, and anything that needs engineering judgement goes to your engineers. Each decision, reviewer and date is kept, and the reports build themselves.

XLSXEvery element, every input, every result.
PDF reportThe narrative an auditor reads first.
Gaps reportOnly what fails or is missing, with the source.
Pre-filled RSAWThe worksheet, populated from the run.

How the logic is built, tested and kept current →

05 / Evaluate it on evidence

Make the next demo an audit rehearsal.

Whether you evaluate data phleet or another vendor, ask to follow one finding all the way back to the file.

Plan your evaluation
  1. Find the original input.Which file, revision, page and extracted value support the answer?
  2. Inspect the method.Which requirement and rule version were applied? Would the same records give the same result next year?
  3. Test an incomplete record.Does missing information become a visible gap for review?
  4. Follow the approval.Who reviews the finding, and how is their decision preserved?
  5. Take the evidence with you.Inspect the workbook, report, gaps and pre-filled RSAW.
Download the vendor evaluation checklist ↓

Compare software, consultants and tracking platforms →

06 / The AI question

Why not just ask a chatbot?

People are already pasting settings and records into general-purpose AI tools and getting answers that look right. Two problems. A probabilistic model can give a different answer to the same question tomorrow, and it can't show an auditor a fixed method. And the data you paste (settings, topology, ratings) may be BES Cyber System Information you've promised to protect under CIP-011.

We use machine learning where it's good, which is reading messy documents. Deciding whether the evidence is complete is deterministic code. That split is the whole design.

Read our guide to using AI in NERC compliance safely →

07 / Built with compliance people

The question an auditor asks isn’t “does this look right?” It’s “show me how you know.”

Why every rule is fixed and versioned

Every rule is written with NERC subject matter experts who have spent careers on the other side of the table: former Regional Entity compliance staff, protection and control engineers with 25+ years on high-voltage systems, and O&M teams who run hundreds of plants.

  • NAES Corporation, the largest independent services provider to power generation, has partnered with data phleet since 2023.
  • A leading power-industry consulting firm runs data phleet across hundreds of customer environments.
  • Bring your own consultant: your existing NERC consultants work inside your license, on the same data and logic.
  • Engineering and commissioning firms set up a client's NERC program at COD and keep maintaining it on data phleet. For engineering firms →

Meet the team →

08 / Deployment

CloudAzure-hosted SaaS. TLS in transit, AES at rest, optional de-identified inputs re-associated with your own keys.
HybridDocuments are read and processed inside your network; only results reach the cloud dashboard.
On-premiseThe whole platform, including the document models, behind your firewall. Air-gap capable.

Security, data handling and CIP considerations →

09 / Questions

The short version

What does data phleet do?

data phleet is NERC compliance software for the people who run the compliance program. It surfaces the evidence buried in the records your plants already keep (relay settings files, one-line diagrams, nameplates, maintenance records, disturbance recordings, rosters), organizes it requirement by requirement, flags what is missing, overdue or inconsistent, and builds the evidence package and a pre-filled RSAW. Anything that needs engineering judgement goes to your engineers for review. It currently covers PRC-005-6, PRC-019-2, PRC-024, PRC-025-2, PRC-028-1, PRC-029-1, PRC-030-1, FAC-008-5, CIP-002-5.1a, CIP-003-9 and CIP-004-7, plus asset inventory.

How is that different from GRC or compliance tracking software?

Tracking tools hold whatever evidence your team uploads and remind you when it's due. data phleet reads the underlying records themselves, so it can tell you whether the evidence is actually there: which components lack a maintenance record, which settings sheet is out of date, which event still needs an analysis. Many teams use both: the tracker holds your internal controls and tasks, and data phleet supplies the evidence behind them.

Is data phleet a general-purpose AI tool?

No. Machine learning is used to read documents, such as pulling settings out of a relay file or values off a nameplate. Whether a requirement's evidence is complete is decided by fixed rules written per requirement, so the same records always produce the same result, with the source shown. Missing data is flagged rather than guessed.

Can it run inside our network?

Yes. data phleet runs as Azure-hosted SaaS, as a hybrid where sensitive processing stays on your side, or fully on-premise with nothing leaving your perimeter, including the document-reading models.